Feed-in tariffs for renewable energy and cogeneration (Règlement du 12 février 2008 et du 23 novembre 2012)

Source: International Energy Agency
Last updated: 25 June 2025

The Act on production of electricity based on renewable energy sources establishes system of certificates guaranteeing renewable origin of the electricity produced. Certificates are necessary for the administration purposes and dealings between plant’s owner and network operator and other administrative purposes.


 


The Act outlines method of calculating feed-in tariff (FIT) levels for renewable energy electricity. 


FIT levels vary depending on the renewable energy source and generation capacity of the plant.


FITs are being guaranteed for a period of 15 years for all types of renewable plants counting from the year when the plant was connected to the national grid.





















































































Renewable source



Power plant capacity



Period of time



Feed-in tariff in EUR/MWh



Yearly reduction



Additional bonus in EUR/MWh



Wind



All sizes



15 years



82.70



0.25%



N/A



Solar PV rooftops



< 30 kW



420



3%



30 kW – 1MW



370



Hydro



< 1 MW



105



0.25%



1 – 6 MW



85



Biogas



< 150 kW



150



EUR 30/MWh under certain conditions



150 – 300 kW



140



300 – 500 kW



130



500 kW – 2.5 MW



120



Wastewater



All sizes



65



N/A



Solid biomass



< 1 MW



145



EUR 30/MWh under certain conditions



> 1 MW



125



Wood waste



< 1MW



130



1 – 5 MW



110



The Act introduces additional bonus for commercialised heat generated by combined heat and power based on biomass, biogas and wood waste. Bonus is paid on top of the feed-in tariff. The level of the bonus is EUR 30/MWh. In order to benefit from the additional premium certain conditions must be met.