In March 2011 Renewable Energy Independent Power Producer Programme (REIPPP), a public procurement programme, replaced the Feed-in Tariff system, which was introduced in 2009.


Qualifying technologies: onshore wind, solar PV, solar thermal, biomass solid, biogas, landfill gas and small hydro plants.


A ceiling tariff level is established for each technology in the auctions. Winning bidders sign PPAs, which are guaranteed for a period of 20 years.


From 2011 to the beginning of 2015 five rounds of reverse auctions were held for construction and supply of 3,625MW of large-scale (>5MW) renewable energy capacity. 







































Results of the auction rounds



Auction number



Auction date



Capacity allocated



Round 1



7 December 2011



1.4 GW



Round 2



21 May 2012



1 GW



Round 3



29 October 2013



1.4 GW



Round 4



11 April 2015



200 MW allocated to solar thermal



Round 5



25 June 2015



Results not announced yet