Diversification and strengthening of electrical interconnections
'Adriatic link: CC connection between Abruzzo and Marche was authorized by decree of January 31, 2024, scheduled for operation in 2028. Adriatic backbone (Foggia – Villanova power line) is in the authorization phase with operation scheduled for 2028-30. Montecorvino – Avellino Nord – Benevento power line in the planning phase with operation scheduled for 2028/29. Reorganization of the northern Calabria network in the planning phase with operation scheduled for 2030. Aliano – Montecorvino electrode planned with operation scheduled for 2032. Northern Benevento area power line planned with operation scheduled for 2035.
Want to know more about this policy ? Learn more