Country:Democratic Republic of the Congo
Year:2007
Policy status:In Force
Jurisdiction:National
Date Effective:2007
Policy Type:Regulatory Instruments, Regulatory Instruments>Auditing
Policy Target:Multiple RE Sources, Multiple RE Sources>All
Policy Sector:Framework Policy
Size of Plant Targeted:Small and Large
Agency:World Bank
URL:http://www-wds.worldbank.org/external/default/WDSContentServer/WDSP/AFR/2015/04/15/090224b082dc2082/1_0/Rendered/PDF/Africa000Regio0Report000Sequence015.pdf
Description:

The objective of the project is to improve operational efficiency in the electricity sector and expand renewable generation, transmission and distribution capacity in order to better serve domestic power demand and to support regional power market integration. The anticipated exported renewable energy to the Southern African Power Pool (SAPP) when the project comes on-line  is 1,349 GWh per year.

 

Last modified: Fri, 02 Mar 2018 10:33:11 CET