India 175 GW Renewable Energy Target for 2022

Source: International Energy Agency
Last updated: 12 May 2021
In 2015 India’s Ministry of New and Renewable Energy adopted new renewable energy target of 175 GW to be achieved by 2022. The majority of the targeted capacity is to come from solar PV – 100 GW, followed by 60 GW from wind and residue capacity split between biomass (10 GW) and small hydropower stations (5 GW).Prior 2015, the solar PV capacity target for 2022 was 20 MW.India established tentative state targets braked down by technology (to see those, please see above link). The regional technology targets are as followRegionPV (MW)Wind (MW)Small Hydro Power (MW)Biomass (MW)Northern Region31120860024504149Western Region28410226001252875Southern Region265312820016752612Eastern Region12237 135244North Eastern Region1205 615 All India9953360000500010000